Showing posts with label Misc : Open Access. Show all posts
Showing posts with label Misc : Open Access. Show all posts

Open Access : In Indian Railway


Indian Railway Moving Towards Open-Access

Why?:- Energy costs constitute 24.16% of ordinary working expenses of Indian Railways. Hence, Indian Railways’ Energy Policy and Management has been issued on 03rd November, 2016 by honorable Executive director (Electrical Energy Management) Ministry of Railways. Under this policy railway has prepared a plan to curtail this huge expenses. Open Access is one of the item of the plan.                     

Target?:- Indian Railways is moving towards Open Access to curtail electric traction energy bill. For this Indian Railways has started Mission 41K. The estimated savings on these accounts indicates that in ten years (2015-2025), these initiatives can generate a cumulative saving of about ₹41,000 cr. in electric traction bill, which has been named as IR’s Mission 41K.


Initiatives? :- With a view to effect savings in its huge energy bill, Indian Railways took lot of innovative initiatives in arranging procurement of power under open access. It may be pointed out that the Electricity Act 2003 conferred Deemed Licensee status on IR due to its involvement in generation, transmission & distribution of energy from the time electricity came to India. Accordingly, IR had been working to get this provision of Electricity Act operational; however it didn’t come through for quite some time due to various factors.

Later, however, Minister of Railways, took up this task with fresh impetus and subsequently a strategy was drawn. In line with this, Indian Railway approached Central Electricity Regulatory Commission (CERC) for issue of necessary guidelines to all State Transmission Utilities (STUs) and State Load Dispatch Centres (SLDCs) to facilitate Open Access to Indian Railways on existing transmission network as Deemed Licensee.

Finally, IR’s vision of drawing electrical energy as deemed licensee was realized on 26th Nov.’15 when it started drawing about 200 MW power on Central Railway from Ratnagiri Gas Power Pvt. Ltd. {RGPPL – Gas based power plant} in Maharashtra.
This was for the first time that IR had drawn energy under open access as a distribution licensee using state distribution network. 

IR contracted about 500 MW from RGPPL for consumption in the states of Maharashtra, Gujarat, M.P., and Jharkhand for meeting its electric traction power requirement. The flow of power in all these four States was completed by 22nd Jan.’16. IR also contracted 50 MW through open tender for taking power on its own transmission network from Dadri to Kanpur, which started flowing from 1st Dec.’15. Further in the current year flow of power started in the state of Rajasthan from 1st Jan’2017, in Damodar Valley Corporation (DVC) area from Aug’17 and in the states of Haryana and Karnataka from Oct’17.

With continuous efforts from Ministry of Railways and the support provided by Govt. of India including PMO office, on date Electric traction power is presently being sourced through Open Access route in 7 states (Maharashtra, Gujarat, M.P, Jharkhand, Rajasthan, Haryana and Karnataka) and DVC area.Moreover, the states of Bihar, Uttar Pradesh, West Bengal, Tamil Nadu and Telangana have also agreed to permit Railway for flow of power though Open access route which is likely to start by next year. The talks of Indian Railways with remaining states are going on for procuring power through open access route.

As on date out of total requirement of about 2000MW of IR for Electric traction power more than 1000MW is flowing under Open Access. This has reduced the average cost of power in these states where power is flowing under Open Access to about ₹5.00 from earlier cost of more than ₹7.00 per unit. 

Achievements?:- In a major strategy to reduce the cost of its electric traction energy bill, Indian Railways (IR) has succeeded in achieving a cumulative saving of ₹5636 cr. from April, 2015 to October, 2017 against the “Business As Usual” (BAU) mode by procuring power directly under Open Access arrangements. This cumulative figure is likely to further go up to ₹6927 cr. by the end of the current financial year i.e. by March, 2018, which is around ₹thousand crores more than the stipulated target.

Future Planning? :- Immediate benefits that will accrue to Indian Railways by procuring energy as a distribution licensee, and its impact in improving financial performance of IR were enumerated in IR’s Mission 41K document.

These savings will be utilized for taking up Electrification of balance Rail network as part of Mission Electrification. This will further reduce the diesel bill and multiply the savings in energy bill, taking it to about ₹10,500 Cr. per annum in next few years on 100% electrification of IR network.

With success in reducing electric traction bill substantially, mission of bringing down operational cost of Railways has already started taking shape. In due course of time, this will also give shape to the directive of Hon’ble Prime Minister that Railways should play a dominant role in meeting transport needs of the nation in an economical manner, de-congest highways, create more jobs with expansion of rail network and reduce India’s dependence on imported fuel.

Conclusion? :- This humble beginning with cutting input costs will strengthen financial resilience of Railways, improve its resource mobilization, and enable shifting of traffic from road to rail by making it more attractive. Making these savings happen by 2025 will be a real tribute to Indian Railways when it will be celebrating its centenary year of electric traction on Indian Railways.

************************
                                                                                                                              Source : Internet                                                     

Open Access : An Introduction


OPEN ACCESS

What? :- Open Access is one of the most important features of the Electricity Act 2003.  Open Access can be defined as a non-discriminatory provision for use of transmission lines or distribution system or associated facilities with such lines or system by any licensee or consumer or a person engaged in generation in accordance with the regulations specified by appropriate commission.

Why? :- Open access in transmission has been introduces to promote competition amongst the generating companies who can now sell to different distribution licensees across the country. This should lead to availability of cheaper power. It helps large consumers particularly the sick textile, cement and steel industrial units by ensuring regular supply of electricity at competitive rates and boost business of power bourses.
Under Open Access distribution, companies and eligible consumers have the freedom to buy electricity directly from generating companies or trading licensees of their choice and correspondingly the generating companies have the freedom to sell to any licensee or the any eligible consumer.

Category? :-
On the basis of location of buying and selling entity, the open access is categorized as:

Inter State Open Access: When buying and selling entity belongs to different states. In this case CERC regulations are followed. It is further categorized as:
Short Term Open Access (STOA): open access allowed for the period of less than one month.
Medium Term Open Access (MTOA): open access allowed for a period of 3 months to 3 years.
Long Term Open Access (LTOA): open access allowed for a period of 12 years to 25 years.
* If suppose you require open access for two months, then you should re – apply for STOA before the expiry of first month.
Intra State Open Access:  When buying and selling entity belongs to same state. In this case SERC regulations are followed. It is further categorized as STOA, MTOA, and LTOA and the duration of which depends on the respective state open access regulations.

Transactions Type? :-
In general the buyer and seller of electricity can go for bilateral or collective transactions.
Bilateral transactions:  In this transaction, a PPA is signed between the buyer and seller, which is generally facilitated by a trader for a little margin.
Collective transactions: In this transaction the electricity is traded through exchanges, by exchange members for a very small margin fixed by commission. Currently India has two exchanges PXIL and IEX.

Charges? :-
A consumer who is permitted open access will have to make following charges
Connectivity Charges
PoC Charges
Transmission Charges
Transmission Losses
Wheeling Charges
Wheeling Losses
Cross Subsidy Surcharge
SLDC Charges
RLDC Charges
Renewable purchase obligation (RPO)



Some Different Open Access regulations companies? :-
Rajasthan Open Access Regulation
Maharashtra State Electricity Transmission Company Ltd
Andhra Pradesh Open Access Regulation
Punjab State Electricity Transmission Company Ltd
Gujrat Energy Transmission corporation Ltd
Tamilnadu Transmission corporation Ltd

 *********************
                                                                                                                                                                                                            Source : Internet